City of Hood River
Resolution No. 2010-05

A Resolution approving an amendment to the Hood River Waterline Project engineering services contract with Berger/ABAM to add Phase 2 of the Waterline Project and authorizing the City Manager execute a contract amendment.

 WHEREAS, the City of Hood River previously entered into a contract for engineering services with Berger/ABAM on the City’s Waterline Project, Phase 1; and

 WHEREAS, Phase 2 of the Waterline Project is now ready for engineering services and amendment of the Waterline Project Phase 1 engineering contract to add the Phase 2 engineering services in the amount of $981,759; and

 WHEREAS, the City Council considered an amendment of the Berger/ABAM engineering services contract for the Waterline Project to add Phase 2 at its February 8, 2010 regular meeting.

 NOW, THEREFORE, BE IT RESOLVED by the Hood River City Council, acting as the Contract Review Board, hereby approves an Amendment to the engineering services contract with Berger/ABAM for the City’s Waterline Project to add Phase 2 in an amount not to exceed $981,759.  The City Manager shall execute an appropriate amendment to the Berger/ABAM engineering services contract to add engineering services associated with Phase 2 of the City’s Waterline Project.

 Approved by the Hood River City Council, acting as the Contract Review Board, this ____ day of ______________ 2010, to take effect immediately

 

       ______________________________
       Arthur Babitz, Mayor

 

Attest:


     
Jenifer McKenzie, City Recorder Approved as to form:
 

     
Daniel Kearns, City Attorney