Resolution No. 2010-07               
 (A Resolution of the Hood River Urban Renewal Agency
 Providing for Minor Changes to the Columbia-Cascade Development Plan.)

 WHEREAS, Section 1201 of the Columbia-Cascade Development Plan (the Plan) defines minor changes in the Plan as those which do not modify the goals and objectives of the Plan or its provisions. 

 WHEREAS, the third amendment to the Plan was approved via Ordinance No. 1573 in June of 1998.  The report accompanying Ordinance No. 1573 details the remaining projects in existence at that time and reflects the intent of the Hood River Urban Renewal Agency (Agency) to complete construction of the itemized projects and recognized that the Agency anticipated that the itemized projects would be completed prior to 2013. 

 WHEREAS, the Agency has determined that it is appropriate to amend the report which accompanies the third amendment to the Plan to provide anticipated completion dates for those projects which have not yet been completed as of the date of this resolution.

 Now, therefore, the Hood River Urban Renewal Agency resolves as follows:

 The report on the third amendment to the Plan is amended to provide the anticipated completion dates for each of the remaining projects, as follows:

Project No. Description  Anticipated Completion Date
  Pedestrian Amenities (Projects 64 through 76)  
65  Oak Street - Front Street to 220' west of 6th Street  December 31, 2010
    
  Water Delivery System (Projects 1 through 17)  
11  6th Street - Cascade Oak Street to Wasco Street Extension  December 31, 2010
  (Cascade to State Remaining)  
  Local & Arterial Street (Projects 41 through 59)  
55  6th Street - State to Cascade   December 31, 2010
  Pedestrian Amenities (Projects 64 through 76)  
70  6th Street - State to Cascade   December 31, 2010
    
  Water Delivery System (Projects 1 through 17)  
3  Oak Street - Front St. to 7th Street  June 30, 2011
  (Front Street to 1st Street remaining)  
17  Front Street - State Street to Oak Street  June 30, 2011
  Sanitary Sewer System (Projects 18 through 30)  
20  Oak Street - Front St. to 7th Street  June 30, 2011
  (Front Street to 1st Street remaining)  
30  Front Street - State Street to Oak Street  June 30, 2011
  

Storm Drainage System (Projects 31 through 40)  
39  Catch Basins, inlets, manholes and drainage pipes   June 30, 2011
  (Oak Street from 1st to Front Remaining)  
  Local & Arterial Street (Projects 41 through 59)  
42  Oak Street - Front St. to 7th Street  June 30, 2011
  (Oak Street from 1st to Front Remaining)  
49  Front Street - State Street to Oak Street  June 30, 2011
  Pedestrian Amenities (Projects 64 through 76)  
65  Oak Street - Front Street to 220' west of 6th Street  June 30, 2011
  (Oak Street from 1st to Front Remaining)  
76  Front Street - State Street to Oak Street  June 30, 2011
    
  Water Delivery System (Projects 1 through 17)  
2  State Street - 220' feet west of 6th Street to 13th Street  December 31, 2011
  Sanitary Sewer System (Projects 18 through 30)  
19  State Street - 220' feet west of 6th Street to 13th Street I/O  December 31, 2011
  Storm Drainage System (Projects 31 through 40)  
32a  State Street - 220' feet west of 6th Street to 13th Street I/O  December 31, 2011
  Local & Arterial Street (Projects 41 through 59)  
59  State Street - 220' feet west of 6th Street to 13th Street I/O  December 31, 2011
  Pedestrian Amenities (Projects 64 through 76)  
64a  State Street - 220' feet west of 6th Street to 13th Street   December 31, 2011
    
  Water Delivery System (Projects 1 through 17)  
1  State Street - HR Bridge to 220' west of 6th Street  December 31, 2012
  Sanitary Sewer System (Projects 18 through 30)  
18  State Street - Front Street to 220' west of 6th Street  December 31, 2012
  Storm Drainage System (Projects 31 through 40)  
31  State Street - Eastern UR Boundary to Hood River outfall I/O  December 31, 2012
32  State Street - Eastern UR Boundary to 220' west of 6th Street December 31, 2012
  Local & Arterial Street (Projects 41 through 59)  
41  State Street - HR Bridge to 220' west of 6th Street  December 31, 2012
  Pedestrian Amenities (Projects 64 through 76)  
64  State Street - Front Street to 220' west of 6th Street  December 31, 2012

 Approved by the Hood River Urban Renewal Agency on the 18 day of February, 2010.

     Hood River Urban Renewal Agency


     By:                                                                
           Robert Hastings, Chair

_____________________________
Jennifer McKenzie, City Recorder